Another milestone following blast furnace restart
16 January 2025
The resumption of steel production in the Whyalla Steelworks has reached another milestone with the Rolling Mill also successfully starting up, meaning all operational units are now back in operation.
The rolling mill was successfully brought back online in a carefully planned and executed operation and is now working through customer orders.
“It’s inspiring to see the skill and dedication which has seen the final piece in the steelworks puzzle come alive once again,” GFG Alliance Chief Manufacturing Officer Theuns Victor said.
“The Blast Furnace is operating at more than 70% of its capacity whilst the Steelmaking facility and the Rolling Mill are converting the Hot Metal into our quality Australian made product for our domestic customers.
“Although there is still a long road ahead on our journey back to black, we do want to also celebrate the special efforts by the Whyalla team to get us this far.”